A critical activity is
A) an activity that consumes no time but shows precedence between events.
B) a milestone accomplishment within the project.
C) an activity with zero slack.
D) the beginning of an event.
Correct Answer:
Verified
Q21: Arcs in a project network indicate
A)completion times.
B)precedence
Q22: The main difference between CPM and PERT
Q23: PERT and CPM
A)are most valuable when a
Q24: When activity times are uncertain,
A)we assume they
Q25: Activities following a node
A)can begin as soon
Q27: Activities K,M,and S immediately follow activity H,and
Q28: Activities with zero slack
A)can be delayed.
B)must be
Q29: In deciding which activities to crash,one must
Q30: Slack equals
A)LF - EF.
B)EF - LF.
C)EF -
Q31: For an activity with more than one
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents