Solved

A Senior MIS Design Class Project Team Has Developed the Following

Question 49

Essay

A senior MIS design class project team has developed the following schedule of activities for their project,using their best estimate of completion times.Both written and oral reports are required.Draw the project network.Can they complete the project in the 38 class days remaining until the end of the semester?  Activity  Time  Immediate Predecessor  A.  Find dient 4 B.  Write prospectus 2 A  C.  Obtain approval from client and professor 3 B D.  Complete programming 12C E.  Do industry background research 10 F.  Write final paper 6 D, E  G.  Write oral report 5 D, E \begin{array} { l l c c } & { \text { Activity } } & \text { Time } & \text { Immediate Predecessor } \\\hline \text { A. } & \text { Find dient } & 4 & \cdots \\\text { B. } & \text { Write prospectus } & 2 & \text { A } \\\text { C. } & \text { Obtain approval from client and professor } & 3 & \mathrm {~B} \\\text { D. } & \text { Complete programming } & 12 & \mathrm { C } \\\text { E. } & \text { Do industry background research } & 10 & \cdots \\\text { F. } & \text { Write final paper } & 6 & \text { D, E } \\\text { G. } & \text { Write oral report } & 5 & \text { D, E }\end{array}

Correct Answer:

verifed

Verified

blured image and the c...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents