For a construction contract where the company uses the percentage of completion method and there is a change in the estimated total cost of the contract from 12 million to 13 million, the accountant should do the following:
A) Use the average cost of 12.5 million.
B) Compute the percentage completed using the new cost total if the company uses the cost ratio to estimate percentage completed.
C) Use estimated costs determined at the beginning of the contract, not actual costs to date.
D) Use retrospective treatment.
Correct Answer:
Verified
Q29: Define the term "prospective adjustment." Which type
Q30: How should enterprises reflect changes in accounting
Q31: How many balance sheets are required by
Q32: Why is the prospective treatment conceptually appropriate
Q33: A retailer increases bad debts expense from
Q34: During the audit of Keats Island Brewery
Q35: What types of accounting changes are treated
Q36: Albacore Sailboats manufactures small sailing dinghies. In
Q37: What are two reasons why an accounting
Q38: An analysis of a company's inventory indicates
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents