Solved

For a Construction Contract Where the Company Uses the Percentage

Question 39

Multiple Choice

For a construction contract where the company uses the percentage of completion method and there is a change in the estimated total cost of the contract from 12 million to 13 million, the accountant should do the following:


A) Use the average cost of 12.5 million.
B) Compute the percentage completed using the new cost total if the company uses the cost ratio to estimate percentage completed.
C) Use estimated costs determined at the beginning of the contract, not actual costs to date.
D) Use retrospective treatment.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents