Kent Corp(KC),general Contractors Building a New Dorm at a University,contracted with with Fine
Kent Corp.(KC),general contractors building a new dorm at a university,contracted with Fine Rugs Inc.(FRI)to have certain grade of industrial rugs installed in the dorm.The contract price was $180,000.After the rugs were installed,KC was dissatisfied with the rug quality.FRI insisted that the rugs installed were appropriate to the contract specifications and demanded full payment.KC sends FRI a check for $120,000 which they believe is the proper value for the rugs installed and they mark the check,"Paid in Full".FRI writes "Under Protest" and deposits the check.FRI may now,in most states,successfully sue KC for the balance of $60,000.
Correct Answer:
Verified
Q21: Lance is an avid bicyclist and sends
Q21: Assignments require the consent and agreement of
Q23: Anticipatory repudiation may be used when a
Q25: Generally,courts do enforce a strict compliance standard
Q26: Impossibility of performance is subjective,meaning that one
Q28: Mel is under contract with a textbook
Q29: Substantial performance will be enforced only if
Q32: Patios R Us contracts with Karl's Concrete
Q34: Kathy and Tom have entered into a
Q35: Specific performance is almost always available when
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents