End item A is made by assembling 2 parts of B and 4 parts of C. Part C is made from 3 parts of D and 2 parts of E. Gross requirements for end item A are 100 units. What is the net requirement for part C?
A) 70 units
B) 200 units
C) 125 units
D) 100 units
Correct Answer:
Verified
Q3: A master production schedule shows the following
Q4: End item A is made by assembling
Q6: The longest lead-time path in the BOM
Q6: Jones Company uses widgets as component parts.
Q9: MRP is a process that would be
Q10: A master production schedule shows the following
Q11: Using the BOM, if 2 units of
Q12: The quantities of end items to be
Q14: Planning for which of the following products
Q17: Significant changes in an MPS quantity several
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents