Leonesio Corporation makes a product that uses a material with the following standards:
The company budgeted for production of 3,100 units in August, but actual production was 3,200 units. The company used 27,600 kilos of direct material to produce this output. The company purchased 29,000 kilos of the direct material at a total cost of $118,900. The direct materials purchases variance is computed when the materials are purchased.
-The materials price variance for August is:
A) $2,900 U
B) $2,624 U
C) $2,900 F
D) $2,624 F
Correct Answer:
Verified
Q75: Luma Inc. has provided the following data
Q76: Bumgardner Inc. has provided the following data
Q77: Leonesio Corporation makes a product that uses
Q78: Bumgardner Inc. has provided the following data
Q79: The following materials standards have been established
Q81: Bulluck Corporation makes a product with the
Q82: Pippin Inc. has provided the following data
Q83: Bulluck Corporation makes a product with the
Q84: Pippin Inc. has provided the following data
Q85: Bulluck Corporation makes a product with the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents