If Coffee Company has a safety stock of 400 units and the average daily demand is 30 units,how many days can be covered if the shipment from the supplier is delayed by 12 days?
A) 1,200 days
B) 15 days
C) 13.3 days
D) 21.5 days
E) 14 days
Correct Answer: