Dynamo Building Supply Company's operational management is calculating the variable overhead efficiency variance for 2011.The machine hour cost per unit was calculated to be 0.40 hours and the company budgeted for 20,000 units.However,the actual quantity of variable overhead hours amounted to 8,500 after computation.The budgeted overhead cost per unit has been determined to be $40 per hour.
Required
Compute the variable overhead efficiency variance and identify whether the variance if favorable,F,or unfavorable,U.
A) $15,000;U
B) $20,000;U
C) $5,000;U
D) $20,000;F
E) $15,000;F
Correct Answer:
Verified
Q1: The planning of fixed overhead costs differs
Q61: What is the purpose of standard costing?
Q62: Which of the following steps is not
Q63: Fixed overhead costs are,by definition,a lump-sum of
Q64: Delicious Dishes Company is developing the budgeted
Q65: A flexible budget allows management to highlight
Q67: Variable overhead flexible-budget variance measures the difference
Q68: Why is constructing and using a flexible
Q69: A manager should not always view a
Q70: Atlas Cable Company has a total variable
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents