A company produces two end-items: products A and B. They are concerned about the loading on their Finish Shop and are trying to develop a rough-cut capacity plan. To finish product A two hours are required and for product B one hour. Total hours available in the Finish Shop are 100. They have the following weekly production information:
a.What is the total hourly load on the Finish Shop in week 3?
b.In what week is the Finish Shop overloaded?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q62: A company makes traffic signals for downtown
Q64: A sheet metal company has developed the
Q65: Explain how a bill of materials (BOM),
Q66: A hardware company is interested in developing
Q66: Given the information below, complete the MRP
Q68: The bill of material for end item
Q72: Explain the three levels of resource planning.
Q80: Pacific Chemical Products, Inc.produces a liquid laundry
Q84: A metal shop currently has a work
Q96: What is capacity requirements planning (CRP)?
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents