A print shop has four jobs that have to be processed through their only five-color press.They usually use the first-come first-served method of scheduling jobs.However, the customers are waiting in the lobby for these jobs so the shop wants to minimize the average waiting time.They are going to use the shortest processing time rule to do so.Processing times for each job are as follows (assume this is the arrival order): Job A, 30 minutes; Job B, 17 minutes; Job C, 12 minutes; Job D, 39 minutes.
a.In what order should the four jobs be done using the shortest processing time rule?
b.What is the average waiting (flow) time for all jobs using the shortest processing time rule?
c.What is the averaging waiting (flow) time using their usual first-come first-served rule?
Correct Answer:
Verified
Order of job...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q57: A restaurant needs the following number of
Q58: Give at least five examples of service
Q59: The following five jobs, along with their
Q60: ScheduleAnywhere.com on-line software helps clients do all
Q61: An airplane repair facility has a contract
Q61: Explain the three categories of criteria used
Q62: A print shop has five large commercial
Q63: A young entrepreneur has just opened an
Q64: At the end of each month, a
Q66: A company is faced with seven tasks
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents