Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is A - D - H - I - J - K.
a.Determine the standard deviation of the critical path.
b.Determine the probability of completing the project in 38 weeks or less.
c.What is the probability of completing the project in 32 weeks or less?
Correct Answer:
Verified
Q41: Explain the role of the project managers
Q42: A company has a PERT project with
Q43: You are in charge of the "advertising
Q45: You are responsible for managing an advertising
Q47: Consider the project network and data shown
Q51: The following network shows all the major
Q81: Describe the four major steps in the
Q95: Explain the three time estimates used to
Q97: Describe how a project fits into each
Q99: Define critical path and explain how it
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents