A company has used PERT for a project and wants to minimize the probability of overrunning a contract deadline of 30 weeks. Three paths of concern in the PERT network have these mean durations and variances in weeks:
a.What is the Z-score for path 1?
b.What is the probability of path 2 overrunning the deadline?
Correct Answer:
Verified
Q51: The following network shows all the major
Q52: Explain the stages of the project life
Q52: The following network shows the activities on
Q53: Consider the project network and data shown
Q55: The network below represents a project being
Q60: An electrical contracting company has been awarded
Q81: Describe the four major steps in the
Q83: List at least six principal factors (contributors)
Q94: Explain the purpose of Gantt charts.
Q96: Define a project. Give some non-manufacturing or
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents