You are responsible for managing an advertising and promotion project with the following activities (times are given in weeks).
a.What is the critical path and expected completion time for this project?
b.Which activity has the largest slack, and how large is that slack?
c.What is the probability that the project will be completed within 16 weeks?
d.If the expected time (not the most likely time) for activity B is changed to 18 weeks from 11 weeks, by how many weeks will the project's expected completion time increase?
Correct Answer:
Verified
b....
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q38: Which of the following is least related
Q41: Explain the role of the project managers
Q42: A company has a PERT project with
Q43: You are in charge of the "advertising
Q46: Data regarding the activities for a project
Q47: Consider the project network and data shown
Q81: Describe the four major steps in the
Q95: Explain the three time estimates used to
Q97: Describe how a project fits into each
Q99: Define critical path and explain how it
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents