Coral Corporation builds large cruise ships on a contract basis.The company uses the percentage of completion method of revenue recognition.The following information pertains to the construction contracts it had in place as of its December 31,2018 year-end.
Required:
a.Calculate the revenue to be recognized in 2017 and in 2018.
b.While examining the Coral financial statements,the auditors noted that there was an error in the estimate of costs to complete the contracts in 2017.The cost to complete should have been $600 million instead of $800 million.Explain how this would be accounted for in the financial statements.
c.In light of the evidence noted in (b),how much revenue should be recognized in 2018?
Correct Answer:
Verified
2017: $400 million
(Percent complete ...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q92: What are three exceptions to the use
Q98: On July 1,2017,Cusak Construction Company Inc.contracted to
Q100: Smile Operators entered into a contract to
Q101: Apartment King (AK)is building a luxury condominium
Q102: Destiny Apartments Inc.(DA Inc. )is building a
Q104: Creation Construction Company (CCC)has contracted to build
Q105: Community Apartments Inc.(CA Inc. )is building a
Q106: In early 2015,Ecotravel Corp.won a contract to
Q107: Buildings Ltd.is constructing a residential building in
Q108: ACME is investing in a new heavy
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents