Rolling Hills Construction
Rolling Hills Construction Co -The Amount of Overhead Applied for June Is:
A) $3450

Question 38

Multiple Choice

Rolling Hills Construction
Rolling Hills Construction Co. assigns overhead to specific jobs based on direct labour cost (dollars) . The following information is available for the month of June:
 Estimated direct labour hours 2000 hours  Estimated direct labour cost per hour $12/ hour  Estimated overhead costs $3000 Actual direct labour hours 2300 hours  Actual direct labour cost per hour $13 hour  Actual overhead costs $3300\begin{array} { l l } \text { Estimated direct labour hours } & 2000 \text { hours } \\\text { Estimated direct labour cost per hour } & \$ 12 / \text { hour } \\\text { Estimated overhead costs } & \$ 3000 \\\text { Actual direct labour hours } & 2300 \text { hours } \\\text { Actual direct labour cost per hour } & \$ 13 \text { hour } \\\text { Actual overhead costs } & \$ 3300\end{array}
-The amount of overhead applied for June is:


A) $3450.00
B) $3000.00
C) $3737.50
D) $5900.00

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents