Question 54

Essay

The following data are available for Johnson machine builders:
 Estimated direct labour hours 200000 Applied overhead $750000\begin{array}{lr}\text { Estimated direct labour hours } & 200000 \\\text { Applied overhead } & \$ 750000\end{array}

The applied overhead rate is $5 per direct labour hour.
Required:
A. What was the actual direct labour hours for the year?
B. How would your answer to Part A change, if the applied overhead rate was 40 per cent less than given in the question?

Correct Answer:

verifed

Verified

A. Actual direct labour hours blured image actual DL...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents