At a production level of 5,600 units,a project has total costs of $89,000 and a variable cost per unit of $11.20.What is the amount of the total fixed costs?
A) $24,126
B) $26,280
C) $27,090
D) $27,820
E) $28,626
Correct Answer:
Verified