The Elements That Cause Problems with the Use of the IRR

Question 35

Multiple Choice

The elements that cause problems with the use of the IRR in projects that are mutually exclusive are referred to as the:


A) discount rate and scale problems.
B) timing and scale problems.
C) discount rate and timing problems.
D) scale and reversing flow problems.
E) timing and reversing flow problems.

Correct Answer: