What is a disadvantage of actual costing?
A) Actual cost systems cannot provide accurate unit cost information on a timely basis.
B) Actual cost systems produce unit costs that do not change from period to period.
C) Estimates must be used when calculating the actual overhead rate.
D) Problems are created by the calculation of direct labour.
Correct Answer:
Verified
Q30: When can an actual overhead rate be
Q31: Which of the following costs are usually
Q31: When is the predetermined overhead rate usually
Q32: What is the term for the maximum
Q34: Unit costs are critical information for what
Q36: What is the term for the average
Q37: What is the principal difficulty with normal
Q38: What is the term for the production
Q40: What is the term for the association
Q74: Normal costing uses which cost in work
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents