Robin Construction Company Began a Long-Term Contract in 2015

Question 78

Multiple Choice

Robin Construction Company began a long-term contract in 2015.The contract price was $800,000.The estimated cost of the contract at the time it was begun was $500,000.The actual cost incurred in 2015 was $350,000.The contract was completed in 2016 and the cost incurred that year was $125,000.Under the percentage of completion method:


A) Robin should report $300,000 of income in 2015.
B) Robin should report $90,000 of income in 2016.
C) Robin will receive interest (under the lookback method) on the underpayment of taxes in 2015.
D) Robin should report $325,000 of income in 2015.
E) None of the above is correct.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents