Sunshine Contractors started a contract in January 2011 to build a bridge at a fixed price of $14 million. The bridge was to be completed by October 2013. Total cumulative costs incurred by the end of December 2011 and 2012 were $2 million and $6 million, respectively. Sunshine is unable to estimate the total costs of the project prior to completion. Final costs at the end of the project totaled $11 million. How much cost of sales will Sunshine report in 2013?
A) $3,000,000
B) $5,000,000
C) $8,000,000
D) $11,000,000
Correct Answer:
Verified
Q74: Which statement best explains the percentage of
Q74: Jones Contractors Inc. agreed to construct a
Q75: Explain how a company records revenue and
Q75: Nichols Construction Company (NCC)entered into a contract
Q78: Yang Construction Company entered into a contract
Q80: Nichols Construction Company (NCC)entered into a contract
Q81: Which statement is correct about the "winner's
Q83: Briefly explain the following terms:
a)Non-monetary exchange transaction
b)Consignment
Q84: How is income and expense recognized for
Q99: Which statement is correct about the impact
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents