Coral Corporation builds large cruise ships on a contract basis. The company uses the percentage of completion method of revenue recognition. The following information pertains to the construction contracts it had in place as of its December 31, 2012 year-end.
Required:
a. Calculate the revenue to be recognized in 2011 and in 2012.
b. While examining the Coral financial statements, the auditors noted that there was an error in the estimate of costs to complete the contracts in 2011. The cost to complete should have been $600 million instead of $800 million. Explain how this would be accounted for in the financial statements.
c. In light of the evidence noted in (b), how much revenue should be recognized in 2012?
Correct Answer:
Verified
2011: $400 million
(Percent complete ...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q100: Which accounting method is permitted under ASPE
Q101: Soorya Manufacturing makes educational toys that are
Q102: ACME is investing in a new heavy
Q103: Community Apartments Inc. (CA Inc.)is building a
Q104: Explain whether each of the following transactions
Q105: Apartment King (AK)is building a luxury condominium
Q106: Buildings Ltd. is constructing a residential building
Q107: In early 2009, Ecotravel Corp. won a
Q108: Destiny Apartments Inc. (DA Inc.)is building a
Q110: Creation Construction Company (CCC)has contracted to build
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents