Which of the following is true of the triple constraint in projects?
A) The time constraint is the most critical of the three constraints in projects.
B) The three fundamentals that are known to constrain projects are insulated from each other.
C) Changes in one fundamental constraint force changes in the other constraints as well.
D) Cost constraints take precedence over time and scope constraints in all projects.
Correct Answer:
Verified
Q24: A black swan refers to those favorable,
Q26: Which of the following is a difference
Q28: How does a project charter help in
Q29: A _ helps to avoid unexpected surprises
Q29: A _ is a series of events
Q30: A(n)_ is an initiating process where stakeholders
Q31: Which of the following functions does a
Q34: Which of the following best describes a
Q35: The stage at which early phase managers
Q36: A(n) _ is a temporary activity that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents