A(n) ________ in a work breakdown structure refers to a task that needs to be completed before a particular task can begin.
A) subtask
B) successor
C) concurrent
D) predecessor
Correct Answer:
Verified
Q41: In which of the following project management
Q43: Which of the following best describes deliverables
Q47: The _ process in project management focuses
Q48: In the _ phase, project managers pay
Q48: A(n) _ is a document which clarifies
Q50: _ track progress from start to finish,
Q50: _ in project management include all the
Q54: In which of the following areas of
Q55: _ refer to products, documents, or services
Q59: A(n)_ is an orderly listing of actual
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents