Which of the following best defines a critical path in a project?
A) the shortest path through a project undertaken to achieve a fixed deadline
B) the longest project path that identifies tasks that cannot be delayed without affecting the finish date
C) the path that takes into account all possible factors that can delay a project to estimate a deadline
D) the shortest path undertaken in a monitoring process in which there is no fixed deadline
Correct Answer:
Verified
Q41: In which of the following project management
Q43: Which of the following best describes deliverables
Q52: Which of the following is an example
Q54: In which of the following areas of
Q55: _ refer to products, documents, or services
Q59: A(n)_ is an orderly listing of actual
Q59: Which of the following best describes a
Q61: The tendency to continue investing in a
Q62: A real estate developer in the New
Q63: Which of the following should a project
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents