The ________ Refers to the Longest Course Through the Project

Question 80

Multiple Choice

The ________ refers to the longest course through the project, which identifies those tasks that can't be delayed without affecting the finish date.


A) clustering coefficient
B) critical path
C) long tail
D) project map

Correct Answer: