A company was experiencing slow production rates, and lower production volumes than demanded by management, so a new factory manager was hired. Upon investigation, she found that the workers were poorly motivated and not closely supervised. Midway through the quarter, she started an incentive program and paid out cash bonuses when workers hit their production targets. Within a short time, production output increased, but the bonuses had to be charged to the direct labor budget, and she was worried about the impact of these costs on operating income. This situation could have produced which of the following variances?
A) Unfavorable materials price variance
B) Unfavorable materials efficiency variance
C) Favorable labor efficiency variance
D) Favorable labor price variance
Correct Answer:
Verified
Q121: A company was experiencing slow production rates,
Q122: Faas Marine Stores Company manufactures decorative
Q123: When completing a standard costing income statement,
Q124: When management is investigating overhead variances, they
Q125: When a manufacturing company uses standard costing
Q127: The production manager of a company was
Q128: The production manager of a company was
Q129: Faas Marine Stores Company manufactures decorative
Q130: The production manager of a company was
Q131: Faas Marine Stores Company manufactures decorative
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents