Job 123 requires $12,000 of direct materials,$5,500 of direct labor,500 direct labor hours,and 300 machine hours.It also requires 6 hours of inspection at $40 per hour.Manufacturing overhead is computed at $30 per direct labor hour used and $40 per machine hour used.
The total amount charged for inspection
A) is $40.
B) is $40 × budgeted hours.
C) is $240.
D) does not figure into the total cost of the job.
Correct Answer:
Verified
Q97: Greatwater Manufacturing uses job costing.In May,material requisitions
Q98: Here are selected data for Campbell Company:
Q99: Here are selected data for Tyler Corporation:
Q100: Davy Company had a beginning work in
Q101: Missy & Daughters allocates manufacturing overhead to
Q103: Here are selected data for Sally Day
Q104: Job 140 requires $12,000 of direct materials,$6,700
Q105: Here are selected data for Stehli Company:
Q106: Here are selected data for Wilson Company:
Q107: Peterson Company gathered the following information for
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents