London Ceramics makes custom ceramic tiles.During March,the company started and finished Job #266.Job #266 consists of 2,500 tiles;each tile sells for $12.00.The company's records show the following direct materials were requisitioned for Job #266.
Basic terra cotta tiles: 2,500 units at $4.00 per unit
Specialty paint: 5 quarts at $7.00 per quart
High gloss glaze: 4 quarts at $12.00 per quart
Labor time records show the following employees worked on Job #266:
Alice Cooper: 18 hours at $24 per hour
Matthew Kline: 20 hours at $13 per hour
Sierra Ceramics allocates manufacturing overhead at a rate of $27 per direct labor hour.
What is the gross profit per tile on Job #266?
A) $12.00
B) $7.28
C) $7.69
D) $11.59
Correct Answer:
Verified
Q177: Ohio Steel uses a job costing system.Ohio
Q178: Shiloh Company uses a job costing system.The
Q179: Deco Corporation uses a job costing system.On
Q180: Sales revenue is $725,000;allocated manufacturing overhead is
Q181: Hollinger Ceramics makes custom ceramic tiles.During March,the
Q183: Records for Speedy's Custom Networks contained the
Q184: London Ceramics makes custom ceramic tiles.During March,the
Q185: Twinkle Ornaments Company uses job costing.Twinkle Ornaments
Q187: Solid Oak Bureau Company uses job costing.Solid
Q189: Omega Technology's work in process inventory on
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents