Simon Manufacturing is conducting preliminary research into installing a geothermal heat pump to heat and cool its factories and offices.The initial cost of installing the new system is $245,000;however,Simon will save $35,000 annually on its heating and cooling costs.The system has an expected life of 15 years.
What is the payback period,in years,for the geothermal heat pump?
A) 7.00 years
B) 4.49 years
C) 25 years
D) 8.56 years
Correct Answer:
Verified
Q12: The "triple bottom line" reports on three
Q35: (Net present value table required)Alexander Industries,in Chicago,plans
Q37: Gluck Metal Works stamps sheet metal into
Q38: Alexander Industries,in Chicago,plans to take advantage of
Q39: Common Paper Supply produces paper cups for
Q42: The new managerial accountant at the Recycle
Q50: The city of Pittsburgh, Pennsylvania conducted a
Q60: Mr. Lite is an entrepreneur that builds
Q80: Materials flow accounting (MFA)reconciles physical output with
Q93: A _ is a measure of the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents