You Are Evaluating Two Projects

Question 62

Multiple Choice

You are evaluating two projects.You may accept only one of them.Project one will cost $379,000 initially and will pay $134,000 each year for the next 5 years.Project two will cost $454,000 initially,but will pay $101,000 for the next 10 years.The firm's cost of capital is 15%.Use the replacement chain approach to compute the NPV of each project.Which project has the highest NPV and by how much? Round your answers to the nearest dollar.


A) Project 2 has a higher NPV by $240,619.
B) Project 2 has a higher NPV by $52,189.
C) Project 1 has a higher NPV by $240,619.
D) Project 1 has a higher NPV by $52,189.
E) The two projects have equal NPV.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents