Ellmann Systems is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that if a project's expected NPV is negative, it should be rejected.
A) $265.65
B) $278.93
C) $292.88
D) $307.52
E) $322.90