A firm is considering a new project whose risk is greater than the risk of the firm's average project, based on all methods for assessing risk. In evaluating this project, it would be reasonable for management to do which of the following?
A) increase the estimated npv of the project to reflect its greater risk.
B) reject the project, since its acceptance would increase the firm's risk.
C) ignore the risk differential if the project would amount to only a small fraction of the firm's total assets.
D) increase the cost of capital used to evaluate the project to reflect its higher-than-average risk.
E) increase the estimated irr of the project to reflect its greater risk.
Correct Answer:
Verified
Q62: Wansley Enterprises is considering a new project.
Q66: Which of the following procedures does the
Q66: The standard deviation is a better measure
Q67: Erickson Inc.is considering a capital budgeting project
Q68: If a firm's projects differ in risk,
Q69: Laramie Labs uses a risk-adjustment when
Q71: Which of the following procedures best accounts
Q72: Sensitivity analysis measures a project's stand-alone risk
Q72: Spot-Free Car Wash is considering a
Q74: McLeod Inc.is considering an investment that has
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents