Whether to invest in a project today or to postpone the decision until next year is a decision facing the CEO of the Aaron Co. The project has a positive expected NPV, but its cash flows could be less than expected, in which case the NPV could be negative. No competitors are likely to invest in a similar project if Aaron decides to wait. Which of the following statements best describes the issues that Aaron faces when considering this investment timing option?
A) the more uncertainty about the future cash flows, the more logical it is for aaron to go ahead with this project today.
B) since the project has a positive expected npv today, this means that its expected npv will be even higher if it chooses to wait a year.
C) since the project has a positive expected npv today, this means that it should be accepted in order to lock in that npv.
D) waiting would probably reduce the project's risk.
E) the investment timing option does not affect the cash flows and will therefore have no impact on the project's risk.
Correct Answer:
Verified
Q2: Real options are most valuable when the
Q8: Garner-Wagner Incorporated
The executives of Garner-Wagner Inc.are considering
Q11: Which of the following is NOT a
Q13: Nationwide Pharmaceutical Corporation
A project with an up-front
Q13: Nationwide Pharmaceutical Corporation
A project with an up-front
Q14: Ashgate Enterprises uses the NPV method for
Q15: Which of the following is most CORRECT?
A)
Q16: The option to abandon a project is
Q17: Which of the following will NOT increase
Q18: Steppingstone Incorporated
The Z−90 project being considered by
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents