Sai Company uses a job order cost system and applies manufacturing overhead costs to jobs using a predetermined overhead rate based on direct labour-hours. The following data were extracted from the company's accounting records for Year 6
Job \#461 was completed during the year and the following costs had been incurred on that job:
-Suppose Job #461 contained 100 units.What unit cost would appear on the job cost sheet for job #461?
A) $55.00 per unit.
B) $61.00 per unit.
C) $61.75 per unit.
D) $62.50 per unit.
Correct Answer:
Verified
Q63: The materials requisition form is a document
Q64: Job-order costing is used in manufacturing companies
Q65: Summit Company has provided the following
Q66: In a job-order costing system,costs are traced
Q67: Summit Company has provided the following
Q69: The Tse Manufacturing Company uses a
Q70: Sai Company uses a job order
Q71: Secrease Corporation uses machine-hours as the
Q72: Sai Company uses a job order
Q73: The Tse Manufacturing Company uses a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents