Lakeside Company Estimated Manufacturing Overhead Costs for 2014 at $378,000

Question 120

Multiple Choice

Lakeside Company estimated manufacturing overhead costs for 2014 at $378,000, based on 180,000 estimated direct labor hours. Actual direct labor hours for 2014 totaled 195,000. The manufacturing overhead account contains debit entries totaling $391,500. The manufacturing overhead for 2014 was: (Round your intermediate calculations to one decimal place)


A) $31,500 underallocated.
B) $31,500 overallocated.
C) $18,000 underallocated.
D) $18,000 overallocated.