London Ceramics makes custom ceramic tiles. During March, the company started and finished Job #266. Job #266 consists of 2600 tiles; each tile sells for $14.00. The company's records show the following direct materials were requisitioned for Job #266. Basic terra cotta tiles: 2600 units at 4.00 per unit
Specialty paint: 7 quarts at $13.00 per quart
High gloss glaze: 14 quarts at $17.00 per quart
Labor time records show the following employees worked on Job #266:
Alice Cooper: 24 hours at $27 per hour
Matthew Kline: 25 hours at $16 per hour
Sierra Ceramics allocates manufacturing overhead at a rate of $30 per direct labor hour.
What is the total amount of direct materials, direct labor, and manufacturing overhead that should be shown on Job #266's job cost record?
A) $11,630
B) $1470
C) $36,400
D) $13,247
Correct Answer:
Verified
Q177: Cooper's Company manufactures custom engines for use
Q178: Calico Corporation produced 2,000 units in Job
Q179: Jasper Carts manufactures custom carts for a
Q180: Job 590 has a total cost of
Q181: Overallocated and underallocated manufacturing overhead is calculated
Q183: Overallocated manufacturing overhead costs occur when the
Q184: Overallocated and underallocated manufacturing overhead is calculated
Q185: The underallocation or overallocation of overhead is
Q186: The amount of overallocation or underallocation is
Q187: Records for Speedy's Custom Networks contained the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents