Gardner Machine Shop Estimates Manufacturing Overhead Costs for the Coming

Question 42

Multiple Choice

Gardner Machine Shop estimates manufacturing overhead costs for the coming year at $316,000. They will allocate based on direct labor hours. Gardner estimates 5,000 direct labor hours for the coming year. What is the predetermined manufacturing overhead rate?


A) $6.32 per direct labor hour
B) $0.016 per direct labor hour
C) $63.20 per direct labor hour
D) $16.00 per direct labor hour