Use this scenario for the following question(s) .
The process design team at a manufacturer has broken an assembly process into eight basic steps, each with a required time, and predecessor as shown in the table. There are 7.5 productive hours available in a day and the manufacturer wishes to produce 400 units. Balance the line by assigning tasks to workstations to fill up as much takt time as possible. Break ties by assigning the longest task first.
-Refer to the scenario above. The process engineer calculates the takt time and examines the task times indicated in the table. He decides to use the minimum cycle time instead and have the workers leave early each day once they have built 400 units. How much earlier would the workers leave?
A) 12 minutes and 53.3 seconds
B) 14 minutes and 20 seconds
C) 16 minutes and 40 seconds
D) 18 minutes and 15 seconds
Correct Answer:
Verified
Q74: Where should a business consultant position herself
Q75: Use this scenario for the following
Q76: Champion Cooling has just signed a
Q77: Which poses the greatest underlying managerial challenges
Q78: Define the terms front room and back
Q80: Use this scenario for the following
Q81: With the backyard poultry craze unleashing
Q82: A manager deciding where six departments could
Q83: The only way to ensure that a
Q84: Use this scenario for the following
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents