Which of these correctly explains the relationship between available to promise inventory and the master production schedule for the first week of the schedule when production is scheduled? Note that ATP is available to promise, MPS is master production schedule, EI is ending inventory, and OB is orders booked.
A) ATP = MPS +
B) MPS = ATP +
C) ATP = EI + MPS -
D) MPS = + ATP - EI
Correct Answer:
Verified
Q3: Given the forecast and booked orders
Q4: Master scheduling accomplishes which of these?
A)calculates the
Q5: The length of time that the master
Q6: Given the forecast and booked orders
Q7: On the master schedule record, the amount
Q9: Given the forecast and booked orders
Q10: Available to promise inventory is always zero
Q11: Which of these statements is best?
A)Master scheduling
Q12: A unit that has not been sold
Q13: Which step in the top down model
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents