Consider the adjacent work stations in this two card kanban system. There is a production card located in the box labeled Outgoing Parts B. Work Center 3 pulls the parts from Work Center 2. Where does the production card go?
A) The production card remains in the same box.
B) The production card is placed at Work Center 3.
C) The production card is placed at Work Center 2.
D) The production card is placed in the box labeled Incoming Parts A.
Correct Answer:
Verified
Q45: In a single-card kanban system:
A)the single card
Q46: The cards employed in a two-card kanban
Q47: Olivia has had enough of the theoretical
Q48: Two announcers are used to read names
Q49: Liversuch Industries uses a kanban system to
Q51: Livermore Industries uses a kanban system to
Q52: In a two-card kanban system:
A)each box of
Q53: A two-card kanban system is a planning
Q54: Two announcers are used to read names
Q55: Consider the adjacent work stations in this
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents