Solved

The Triskaidekaphobia Project Is Starting Its Tenth Week and the Gantt

Question 7

Multiple Choice

The Triskaidekaphobia Project is starting its tenth week and the Gantt chart appears below. Which of these statements about the project is incorrect? The Triskaidekaphobia Project is starting its tenth week and the Gantt chart appears below. Which of these statements about the project is incorrect?   A) The critical path is BCEF. B) Five of the activities are complete. C) Activity D had one week of slack. D) The project is behind schedule.


A) The critical path is BCEF.
B) Five of the activities are complete.
C) Activity D had one week of slack.
D) The project is behind schedule.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents