The Triskaidekaphobia Project is starting its tenth week and the Gantt chart appears below. Which of these statements about the project is incorrect?
A) The critical path is BCEF.
B) Five of the activities are complete.
C) Activity D had one week of slack.
D) The project is behind schedule.
Correct Answer:
Verified