What Is the Fastest Completion Time of the Project with Activity

Question 38

Multiple Choice

What is the fastest completion time of the project with activity lengths (in days) and precedence requirements as shown in the table?  Activity  Length  Predecessor  A 15 B 7 A  C 4 A  D 8 B, C \begin{array} { | c | c | c | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 15 & \cdots \\\hline \text { B } & 7 & \text { A } \\\hline \text { C } & 4 & \text { A } \\\hline \text { D } & 8 & \text { B, C } \\\hline\end{array}


A) 22
B) 25
C) 27
D) 30

Correct Answer:

verifed

Verified