Construction of the Cattery Could Be Distilled to Eight Distinct

Question 30

Multiple Choice

Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Use this scenario to answer the following question(s) .
 Activity  Predecessors  Time (weeks)   A 10 B  A 8 C  A 7 D  C 11 E  D 12 F  B 11 G  E, F 6 H  E, F 9\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & \cdots & 10 \\\hline \text { B } & \text { A } & 8 \\\hline \text { C } & \text { A } & 7 \\\hline \text { D } & \text { C } & 11 \\\hline \text { E } & \text { D } & 12 \\\hline \text { F } & \text { B } & 11 \\\hline \text { G } & \text { E, F } & 6 \\\hline \text { H } & \text { E, F } & 9 \\\hline\end{array}
-Refer to the scenario above. What is the slack for activity G?


A) 4 weeks
B) 3 weeks
C) 2 weeks
D) 1 week

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents