Blues Construction Corp \quad \quad \quad \quad

Question 13

Multiple Choice

Blues Construction Corp. has consistently used the percentage-of-completion method. During 2020, Blues entered into a fixed-price contract to construct an office building for $ 6,000,000. Information relating to the contract is as follows: \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad  At December 31\underline{\text { At December } 31}
Percentage of completionEstimated total cost at completion Gross profit recognized (cumulative) 202015%$4,500,000225,000202145%$4,800,000540,000\begin{array}{c}\begin{array}{lll}\\\\\text {Percentage of completion}\\ \text {Estimated total cost at completion }\\\text {Gross profit recognized (cumulative) }\\\end{array}\begin{array}{r}\underline{2020} \\ 15 \% \\\$4,500,000 \\225,000 \end{array}\begin{array}{r}\underline{2021}\\45 \% \\\$ 4,800,000 \\540,000 \end{array}\end{array}

Under the earnings approach, contract costs incurred during 2020 were


A) $ 1,440,000.
B) $ 1,485,000.
C) $ 1,575,000.
D) $ 2,160,000.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents