Sunshine Contractors started a contract in January 2020 to build a bridge at a fixed price of $14 million. The bridge was to be completed by October 2022 Total cumulative costs incurred by the end of December 2020 and 2021 were $2 million and $6 million, respectively. Sunshine is unable to estimate the total costs of the project prior to completion. Final costs at the end of the project totaled $11 million. How much cost of sales will Sunshine report in 2022?
A) $3,000,000
B) $5,000,000
C) $8,000,000
D) $11,000,000
Correct Answer:
Verified
Q73: Which statement about the percentage of completion
Q74: Which statement best explains the percentage of
Q75: Explain how a company records revenue and
Q76: Algae builds large ships and uses
Q77: Jones Contractors Inc. agreed to construct
Q79: Which statement best explains the cost recovery
Q80: Nichols Construction Company (NCC)entered into a
Q81: Which statement is correct about the "winner's
Q82: Explain whether each of the following
Q83: Briefly explain the following terms:
a)Non-monetary exchange transaction
b)Consignment
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents