Tyco Ltd Entered into a Contract to Build a Sports

Question 68

Multiple Choice

Tyco Ltd entered into a contract to build a sports arena for $1,800,000. Construction commenced on August 1, 2020, with a planned completion date of December 31, 2022. A summary of the related accounting information is provided below: 202020212022 Costs incurred during the year 400,000500,000650,000 Estimated costs to complete at year end 1,200,000600,0000 Billings during the year 560,000640,000700,000 Cash collections during the year 500,000310,000990,000\begin{array} { | l | r | r | r | } \hline & \mathbf { 2 0 2 0 } & \mathbf { 2 0 2 1 } & \mathbf { 2 0 2 2 } \\\hline \text { Costs incurred during the year } & 400,000 & 500,000 & 650,000 \\\hline \text { Estimated costs to complete at year end } & 1,200,000 & 600,000 & 0 \\\hline \text { Billings during the year } & 560,000 & 640,000 & 700,000 \\\hline \text { Cash collections during the year } & 500,000 & 310,000 & 990,000 \\\hline\end{array} How much would the balance in accounts receivable be on the balance sheet of Tyco at the end of 2020 if Tyco uses the percentage of completion method?


A) $110,000
B) $60,000
C) $500,000
D) $660,000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents