Solved

On July 1, 2020, Cusak Construction Company Inc Required:
Using the Percentage of Completion Method, Calculate the Revenue

Question 61

Essay

On July 1, 2020, Cusak Construction Company Inc. contracted to build an office building for Candy Lane Corp. for a total contract price of $2,150,000. On July 1, Cusak estimated that it would take between two and three years to complete the building. In October 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Candy Lane in 2020, 2021, and 2022.
202020212022 Costs incurred to date 340,0001,150,0002,400,000 Estimated costs to complete 1,360,0001,150,0000 Billings to Candy Lane 590,0001,000,0002,100,000\begin{array} { | l | r | r | r | } \hline & 2020 & 2021 & 2022 \\\hline \text { Costs incurred to date } & 340,000 & 1,150,000 & 2,400,000 \\\hline \text { Estimated costs to complete } & 1,360,000 & 1,150,000 & 0 \\\hline \text { Billings to Candy Lane } & 590,000 & 1,000,000 & 2,100,000 \\\hline\end{array} Required:
Using the percentage of completion method, calculate the revenue and profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. The company used the cost-to-cost method to estimate the percentage complete.

Correct Answer:

verifed

Verified

\[\begin{array} { | l | r | r | r | }
\...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents