A job was budgeted to require three hours of labor per unit at $8 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $198,000.
-What is the total labor efficiency variance?
A) $22,000 unfavorable
B) $16,000 unfavorable
C) $6,000 unfavorable
D) $16,000 favorable
E) $22,000 favorable
Correct Answer:
Verified
Q62: Reference: 21_03
Bradford Company budgeted 4,000 pounds of
Q63: Reference: 21_04
A company has established 5 pounds
Q64: Bartels Corp.produces woodcarvings.It takes two hours of
Q65: Reference: 21_05
A job was budgeted to require
Q66: The following company information is available:
Q68: Bartels Corp.produces woodcarvings.It takes two hours of
Q69: The following company information is available:
Q70: Reference: 21_05
A job was budgeted to require
Q71: The following company information is available
Q72: Reference: 21_05
A job was budgeted to require
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents