A company had a $22,000 favorable direct labor efficiency variance during a time period when the standard rate per direct labor hour was $22 and the actual rate per direct labor hour was $21.If the standard direct labor hours allowed for production were 5,000,what is the amount of actual direct labor hours worked during this period?
A) 6,000 hours
B) 4,000 hours
C) 88,000 hours
D) 110,000 hours
E) 22,000 hours
Correct Answer:
Verified
Q75: Overhead cost variance is:
A) The difference between
Q78: The following company information is available:
Q79: Use the following data to find
Q80: Use the following data to find
Q81: A company had a $22,000 favorable direct
Q82: Reference: 21_06
The following information describes a
Q84: The standard materials cost to produce one
Q85: A company established a direct material standard
Q86: Reference: 21_06
The following information describes a
Q88: A company has a standard of 2
Unlock this Answer For Free Now!